Status Updates
December 31, 2025
Beltway Trail Project – Construction Update
We’re pleased to share the latest updates on the Beltway Trail Project!
1. Construction complete
Construction is officially complete, and Owner’s Acceptance was issued on December 16, 2025, marking a major milestone for the project.
2. Upcoming sidewalk revisions
As part of the acceptance agreement, the contractor will be revising sidewalk improvements to address drainage issues at the intersection of Beltway and Belt Line. This work is anticipated to be completed by mid-January 2026.
3. Traffic signage installation
The Public Works Department will be installing updated traffic signage associated with the project. Installation will be prioritized at the start of the new year. Updates to follow.
Thank you for your patience and support as we complete these final items and deliver the full benefits of the Beltway Trail Project to the community.
November 14, 2025
Work on the Beltway Trail Project continues to progress steadily. We’re pleased to share that a substantial completion walkthrough for Phase I is scheduled for the week of November 17th. The design team, Town staff, and the contractor will be onsite to review the completed work and identify any final refinements.
Construction crews have already delivered major elements of the project, including new concrete walking trails, off-street bike lanes, traffic-calming features, sidewalk connections, lighting, and planting.
Stay tuned for more updates as Phase I approaches its finish line.
October 24, 2025
Work on the Beltway Trail Project continues to move forward. Since construction began in February, crews have completed concrete walking trails, off-street bike lanes, traffic calming features, sidewalk connections, and light pole installation. Upcoming work includes planting, roadway striping, and bike lane protectors.
September 12, 2025
Work on the Beltway Trail Project continues to move forward. Since construction began in February, crews have completed concrete walking trails, off-street bike lanes, traffic calming features, sidewalk connections, and light pole installation. Upcoming work includes planting, roadway striping, and bike lane protectors.
As construction progresses, residents have shared feedback about the transition of bike lanes from on-street to off-street near Le Grande Drive. The travel lanes in this area are 12 feet wide, which is consistent with transportation standards, though temporary traffic controls may make them feel narrower during construction.
The Public Works & Engineering Department has made small adjustments, such as modifying traffic delineators and removing temporary striping, to ease the experience in the interim. Staff will continue to monitor this area as work advances and will coordinate with the contractor if refinements are needed as part of the project’s remaining tasks.
When complete, permanent striping and other finishing details are expected to provide clearer guidance for drivers. In addition, traffic calming features like slightly narrower lanes are designed to encourage slower speeds, which can help reduce cut-through driving.
You can follow the progress on the project on the Town's website. Thank you for your patience as we work to make Addison a better place to live, work, and play.
August 22, 2025
Construction on Phase I is well underway, and significant progress has already been made since construction began in February. Below is a summary of the work completed so far and what remains before this phase is finished.
Work Completed in the Greenspace:
-
Demolition and site preparation, including fine grading
-
Concrete walking trails, off street bike lanes, and secondary path installation
-
Traffic calming measures including lane narrowing
-
Electrical work, including installation of the light poles
-
Irrigation system installation (temporary controller in place; permanent controller pending)
-
Planting bed preparation
Work Completed at Beltway Drive and Belt Line Road:
Remaining Tasks:
-
Beltway Trail Connection - detectable warning pavers installation is final item remaining
-
Greenspace planting - tree planting and sod installation are final items remaining
-
Roadway striping and bike lane protector installation from Belt Line Road to the Addison Athletic Club
-
Installation of 3 pieces of art by the Addison Arbor Foundation (outside of Project Scope)
Looking Ahead – Phase II
Phase II of the Beltway Trail Project is scheduled to go out to bid in early September. Construction is expected to begin following the completion of Phase I of the Beltway Trail Project and Phase II of the Les Lacs Pond Project, as both projects share traffic control areas along Beltway Drive. Sequencing these projects ensures efficient progress while minimizing impacts on traffic flow and community access.