Airport Parkway Reconstruction
- Project TypeADA; Bond / CO Project; Drainage Improvements; Sewer; Streets / Sidewalks; Utilities
- Project StatusEngineering Design Phase
Proposition A of the 2019 Bond Program is the reconstruction of Airport Parkway from the Dallas North Tollway to Addison Road. Airport Parkway was originally built in the late 1970s with asphalt and will be rebuilt with concrete. The utilities will be upsized to handle continued growth in Addison, the Master Transportation elements will be installed, and traffic lights will be replaced.
Status Updates
August 26, 2026
The design of the Airport Parkway Reconstruction Project has reached the 95% milestone, and staff is completing the final review of the plans and specifications. The project will transform the existing two-lane asphalt roadway into a durable three-lane concrete street with 11-foot travel lanes in each direction and a 12-foot center lane that will provide dedicated turning areas and landscaped medians where appropriate. The proposed roadway profile also includes ADA-accessible sidewalks, generally six feet wide on both sides of the roadway, and on-street parking in selected areas.
The project will provide a significant visual enhancement to the corridor through new canopy and ornamental trees, irrigated planting beds, shrubs, groundcover, and sod. Additional streetscape features include decorative pedestrian pavers, scored concrete, tree grates, benches, bike racks, trash receptacles, and nearly 80 pedestrian-scale streetlights. Combined with upgraded drainage, utilities, traffic signals, and pedestrian crossings, these improvements will create a safer, more attractive, and more walkable gateway between Addison Road and the Dallas North Tollway.
Staff is working to complete the final design and advance the project into the bidding phase.
May 26, 2026
The final design for Airport Parkway was presented to and approved by Addison City Council.
July 27, 2021
The design is 95% complete. The Town is preparing preliminary right-of-way documents and appraisals for acquisition.
March 9, 2021
The design is 65% complete. Bidding for construction is scheduled to immediately follow the completion of Keller Springs.
August 31, 2020
The 30% conceptual design is complete. The 65% design is estimated to be completed in March of 2021.
December 10, 2019
Council has approved the design contract to Jacobs Engineering.
Resources
Location
Airport Pkwy & Addison Rd, Addison, TX 75001 View Map
32.9660652,-96.82984069999999
Airport Pkwy & Addison Rd ,
Addison, TX 75001
Airport Pkwy & Addison Rd ,
Addison, TX 75001
Airport Parkway Reconstruction