Airport Parkway Reconstruction

  • Project TypeADA; Bond / CO Project; Drainage Improvements; Sewer; Streets / Sidewalks; Utilities
  • Project StatusEngineering Design Phase

Proposition A of the 2019 Bond Program is the reconstruction of Airport Parkway from the Dallas North Tollway to Addison Road. Airport Parkway was originally built in the late 1970s with asphalt and will be rebuilt with concrete. The utilities will be upsized to handle continued growth in Addison, the Master Transportation elements will be installed, and traffic lights will be replaced.


Status Updates

July 27, 2021

The design is 95% complete. The Town is preparing preliminary right-of-way documents and appraisals for acquisition.

March 9, 2021

The design is 65% complete. Bidding for construction is scheduled to immediately follow the completion of Keller Springs.

August 31, 2020

The 30% conceptual design is complete. The 65% design is estimated to be completed in March of 2021.

December 10, 2019

Council has approved the design contract to Jacobs Engineering.