Keller Springs Reconstruction

  • Project TypeADA; Bond / CO Project; Drainage Improvements; Sewer; Streets / Sidewalks; Utilities
  • Project StatusUnder Construction

Proposition A of the 2019 Bond Program is the reconstruction of Keller Springs Road from the Dallas North Tollway to Addison Road. Keller Springs was originally built in the late 1970s with asphalt and will be reconstructed with concrete. The utilities will be upsized to handle continued growth in Addison, the Master Transportation elements will be installed, and the traffic lights at the Quorum Drive intersection will be replaced.


Ways to Stay Informed

  • Subscribe to Email Updates
  • Register for text Updates by texting the word KellerSpring to 888-777
  • Follow @TownofAddison on Facebook and Twitter

Get a Bird's Eye View


Status Updates

July 2024

ONCOR has mobilized back on-site, and four other franchise utilities have now approved permits to conduct their work to move their infrastructure, which is in conflict with the upcoming construction. The Town's contractor is anticipated to mobilize in the next six weeks.

June 2024

The rains in the last few months have significantly slowed the progress of the franchise utility adjustments significantly. Oncor's crews have been rerouted to restore power throughout the metroplex. Once that is complete, they will remobilize to finish up their adjustments.

March 2024

Oncor has begun moving electrical lines to the newly installed electrical poles. Project staff is coordinating with AT&T and Atmos to begin working on adjusting their infrastructure prior to the Town's contractor mobilizing to begin work on the reconstruction project.

January 2024

Oncor Electric has mobilized and began making adjustments to prevent conflicts once major construction activities begin. Telecommunication utilities will also begin to mobilize to adjust their infrastructure as well.

September 2023

The contract was awarded to Tiseo Paving Company during the September 12th City Council meeting. Work is expected to commence in January.

July 2023

Proposals for the Keller Springs Road Utility, Storm, and Pavement Improvements Project were re-advertised in May 2023. Proposals were closed on June 29, 2023. Staff is evaluating the proposals.

January 2023

On October 12, 2022, staff issued a Request for Proposals on CIVCAST as Solicitation #22-72 for the Keller Springs Road Revitalization Project. Proposal responses from two construction companies were opened on November 17, 2022.

The two proposals that were received were over the project budget. Town staff and the design engineer will work together to implement ways to reduce the project cost and make the proposals more competitive.

Staff intends to re-issue the Request for Proposals once the project's scope and design changes are finalized. City Council formally rejected the bids on January 24, 2023.

October 2022

The construction phase for the project is out for bid.

January 31, 2022

The design is 100% complete. Right-of-Way acquisition is still in ongoing negotiations.

July 27, 2021

The design is 95% complete. The Town is preparing preliminary right-of-way documents and appraisals for acquisition.

March 9, 2021

The design is 65% complete. Bidding for construction is scheduled for the late summer of 2021.

August 31, 2020

The 30% conceptual design is complete. The 65% design is estimated to be completed in March of 2021.

December 10, 2019

Council has approved the design contract to Jacobs Engineering.


Resources

Location

Keller Springs Rd & Addison Rd, Addison, TX 75001  View Map

Google Map