Celestial Park Entrance Improvements

 

 

Ways to Stay Informed

Status Updates

Status Updates

December 18, 2025

The Town of Addison is moving forward with the Celestial Park Entrance and Lighting Improvements project to enhance safety, accessibility, and the overall visitor experience at one of our community’s most cherished parks. The project is currently completing the design phase, with construction completion anticipated in FY2026.

Project Highlights

  • Scope: The improvements will address erosion at the southeast entrance, provide ADA-compliant access, and gauge interest in installing new lighting to improve safety along the lawn walking path. The entrance design will be updated to integrate natural materials, and a new lighting plan will be developed.
  • Community Engagement: Residents and park users will have opportunities to provide feedback as the design is finalized. 3D Graphics of the design were presented at the last Town Hall meeting held in November 2025. Feedback was positive all around. See shared graphics below. 
  • Budget: The total project budget is $268,255, funded by the Self-Funded Special Projects Fund and 2022 General Obligation Bonds.
  • Timeline: Design and community engagement are underway. Construction is expected to begin in FY2026, with project completion by the end of that fiscal year.

We look forward to sharing more updates as the project progresses and to welcoming everyone to an improved, safer, and more accessible Celestial Park.

For more information or to provide feedback, please contact the Parks and Recreation Department.

2025-10-29-Celestial-Park_Rendered-Views-Page-003.jpg

 

2025-10-29-Celestial-Park_Rendered-Views-Page-002.jpg

 

Project Timeline

Project Timeline

1. Planning and Design Phase (Current – Q4 2025)

  • Finalize project scope and objectives
  • Review and update entrance design (originally completed in 2020) to integrate natural materials
  • Develop lighting design plan to support existing
  • Community outreach and feedback solicitation
  • Confirm ADA compliance requirements
  • Establish project schedule and key milestones
  • Secure funding and finalize budget allocations
  • Milestone: Completion of planning and design documents

2. Procurement Phase (Q1 2026)

  • Advertise for construction bids
  • Conduct pre-bid meetings and site visits
  • Evaluate bids and select contractor(s)
  • Award construction contract(s)
  • Milestone: Contractor(s) selected and contracts executed

4. Construction Phase (Q2 2026 – Q4 2026)

  • Site preparation and mobilization
  • Ongoing project management and quality control
  • Community updates and engagement
  • Milestone: Substantial completion of entrance and lighting improvements

5. Project Closeout (Q4 2026)

  • Final inspections and punch list completion
  • Project acceptance by the Town
  • Community feedback and post-construction review
  • Finalize project documentation and closeout
  • Milestone: Project completion and opening of improved entrance

 

Project Budget

Project Budget

Component Amount
Entrance Modifications $193,775
Lighting Enhancements $74,480
Total Project Budget $268,255

 

Background

The Celestial Park Entrance and Lighting Improvements project is a comprehensive effort to resolve erosion and safety issues, improve accessibility, and create a more inviting and sustainable entrance to one of Addison’s key parks. The project is fully funded and scheduled for completion in FY2026, with a strong emphasis on community input and high-quality, context-sensitive design.

 

 

 

 

 

 

 