Addison Junction Improvement Project

  • Project TypePublic Infrastructure Improvement Project
  • Project StatusIn Progress



Addison Junction is a transformative mixed-use development project located in the Town of Addison. The project encompasses significant infrastructure improvements, multimodal mobility, utility upgrades, and public realm enhancements designed to support continued growth and connectivity in the community. Current work includes civil infrastructure design, site surveys, and all landscape and hardscape improvements.


Project Timeline

  • Start Date: March 2, 2026
  • End Date: December 31, 2027

Ways to Stay Informed

  • Contact Abdulbasit Abbasi, Capital Improvement Project Manager, at 972-450-2878
  • Follow @TownofAddison on Facebook and Twitter

Status Updates

May 14, 2026

The council has approved the design of Addison Junction with Kimley-Horn. We have held the initial kickoff meeting, during which key points of contact were established.