HSIP- Addison Circle at Quorum Drive, Sojourn Drive and Beltway Drive

  • Project StatusIn Construction



The project includes the installation of rectangular rapid-flashing beacons (RRFBs) at the traffic roundabout at Addison Circle, Quorum Drive, and Beltway Dr.

The contractor will be on site at multiple locations starting November 2, 2026. Traffic control measures will be in place during construction. We encourage everyone to use caution and take the necessary precautions when traveling through the work area.

Addison-RRFBs-3-Locations-Map-1.png

Project Timeline

  • Start Date: October 12, 2026
  • End Date: December 21, 2026

Ways to Stay Informed

  • Contact Abdulbasit Abbasi, Capital Improvement Project Manager, at 972-450-2878
  • Follow @TownofAddison on Facebook and Twitter

Status Updates

November 2, 2026

The project includes the installation of rectangular rapid-flashing beacons (RRFBs) and pedestrian improvements at the traffic roundabout at Addison Circle at Quorum Drive, Sojourn Drive mid-block and Beltway Drive in front of the Addison Athletic Club. The contractor will be on site at multiple locations starting November 2, 2026. Traffic control measures will be in place during construction. We encourage everyone to use caution and take the necessary precautions when traveling through the work area. This project is led and funded by the Texas Department of Transportation.


October 28, 2026

The contractor has installed traffic control measures at all three locations in preparation for construction. The contractor plans to begin on-site work at multiple locations starting November 2, 2026.

Construction activities are expected to take place throughout the project duration. The project team will continue coordinating with the contractor to monitor the schedule, minimize traffic disruptions, and keep the Town of Addison informed of construction progress and any schedule updates.


October 12, 2026

A construction kickoff meeting was held on October 12, 2026, for the HSIP project at Addison Circle, including the intersections of Quorum Drive, Sojourn Drive, and Beltway Drive. The project has a contract duration of 50 working days.