Signal Timing and Hardware Upgrade
January 2001
Project Summary: Provide signal timing and coordination between signals along Belt Line and Midway Roads. This project will provide enhanced traffic progression that will reduce travel times and idling at intersections.
Funding: Estimated Cost: Belt Line Road* Midway Road**
Engineering: $90,000 $52,000
Construction: 610,000 340,000 $700,000 $392,000 *Applications have been made for funding under Dallas County's year 2005 call for projects. Addison's funding share would be a total of $350,000 (50%) if the application is successful. **Dallas County has approved funding in the amount of $196,000(50%). The Town of Addison will be responsible for remaining $196,000.
Schedule:
Belt Line Road: Engineering in FY 2005
Construction in FY 2005-2006
Midway Road: Engineering in FY 2004
Construction in FY 2004-2005 Hurdles: *Securing Dallas County funding. **Securing the Town of Addison 50% match in funding
Design Engineers: None at this time.
Contractor: None at this time.
Project Manager: Robin Jones
Project Number: None at this time.
|