Signal Timing and Hardware Upgrade

Signal Timing and Hardware Upgrade

Signal Timing and Hardware Upgrade

Signal Timing and Hardware Upgrade, Belt Line/Midway Capital Project Summary
January 2001

Project Summary: Provide signal timing and coordination between signals along Belt Line and Midway Roads. This project will provide enhanced traffic progression that will reduce travel times and idling at intersections.

Funding: Estimated Cost: Belt Line Road* Midway Road**

Engineering: $90,000 $52,000

Construction: 610,000 340,000 $700,000 $392,000 *Applications have been made for funding under Dallas County's year 2005 call for projects. Addison's funding share would be a total of $350,000 (50%) if the application is successful. **Dallas County has approved funding in the amount of $196,000(50%). The Town of Addison will be responsible for remaining $196,000.

Schedule:

Belt Line Road: Engineering in FY 2005

Construction in FY 2005-2006

Midway Road: Engineering in FY 2004

Construction in FY 2004-2005 Hurdles: *Securing Dallas County funding. **Securing the Town of Addison 50% match in funding

Design Engineers: None at this time.

Contractor: None at this time.

Project Manager: Robin Jones

Project Number: None at this time.